Graphics Interchange Format  |  1997-06-27  |  40KB  |  432x279  |  4-bit (16 colors)
Labels: text | screenshot | font | number | parallel
OCR: YEAR 2000 COMPLIANCE PROJECT TIMELINE Awareness 48 1% Inventory 2 1% Profect scoping #8 4% Examination, analysis, and solution design 20% Modification 20% Unit test 25% Systems test 150% Integration and user acceptance 5% Implementation, disaster recovery, and documentation 5% 10% 15% 20% 25% 30% Percent of time spent Figure 1: The above graph depicts the estimated breakdown of time spent on each year 2000 project. All stages contain a substantial project management component, which, in stim, add 25 percent in overbend to the overall project.